The Tower Project

Progress on the tower project made so far

Completed
 
November 2022 | ArtArchitects ground-level inspection & preliminary drawings
May 2023 | ArtArchitects appointed for repair project
August 2023 | Measured survey of the tower and spire
September 2023 | Drone survey of the tower and spire
September 2023 | QS Budget estimate
October 2023 | CCCT Fundraising launched
15 November 2023 | Cherrypicker inspection – garden closed
23 November 2023 | Q&A session for local community
5 March 2024 | Netting measurement
7 March 2024 | ArtArchitects Stage 2 Report published
March 2024 | Confirmation of the Brief & Programme, Appointment of Consultants
15-19 April 2024 | Netting installation, garden reopening
May 2024 | Completion of Technical Design
June 2024 | Technical design, DAC application, issued for tender
July 2024 | Tender Returns Received
August/ September 2024 | Preferred Contractor Identified
Future – Target Programme Dependant on Funding:
October/ November | Contract negotiations and Award of Contract
November/ December | Commencement of Site Work
Summer 2025 | Practical Completion