The Tower Project

Progress on the tower project made so far

Completed
 
November 2022 | ArtArchitects ground-level inspection & preliminary drawings
May 2023 | ArtArchitects appointed for repair project
August 2023 | Measured survey of the tower and spire
September 2023 | Drone survey of the tower and spire
September 2023 | QS Budget estimate
October 2023 | CCCT Fundraising launched
15 Nov 2023 | Cherrypicker inspection – garden closed
23 Nov 2023 | Q&A session for local community
5 Mar 2024 | Netting measurement
7 March 2024 | ArtArchitects Stage 2 Report published
 
Future – Target Programme Dependant on Funding:

Mar 2024 | Confirmation of the Brief & Programme, Appointment of Consultants
15-19 April 2024 | Netting installation, garden reopening
May 2024 | Completion of Technical Design
June 2024 | Submit DAC Application, Issue for Tender
July 2024 | Tender Return and Award of Contract
August 2024 | Commencement of Site Work
Spring 2025 | Practical Completion