The Tower Project

News, updates and timeline
November 2022

ArtArchitects ground-level inspection & preliminary drawings

November 2022
May 2023

ArtArchitects appointed for repair project

May 2023
August 2023

Measured survey of the tower and spire

August 2023
September 2023

Drone survey of the tower and spire

September 2023
September 2023

QS Budget estimate

September 2023
October 2023

CCCT Fundraising launched

October 2023
15 November 2023

Cherrypicker inspection – garden closed

15 November 2023
23 November 2023

Q&A session for local community

23 November 2023
5 March 2024

Netting measurement

5 March 2024
7 March 2024

ArtArchitects Stage 2 Report published

7 March 2024
March 2024

Confirmation of the Brief & Programme, Appointment of Consultants

March 2024
15-19 April 2024

Netting installation, garden reopening

15-19 April 2024
May 2024

Completion of Technical Design

May 2024
June 2024

Technical design, DAC application, issued for tender

June 2024
July 2024

Tender Returns Received

July 2024
August/ September 2024

Preferred Contractor Identified

August/ September 2024
January 2024

Contract negotiations and Award of Contract

January 2024
February 2025

Commencement of Site Work

February 2025
October 2025

Practical completion

October 2025